If Ralph can determine a schedule for releasing red-tag materials based on the bottlenecks, he can also determine a schedule for final assembly. Once he knows when the bottleneck parts will reach final assembly, he can calculate backwards and determine the release of the non-bottleneck materials along each of their routes. In this way, the bottlenecks will be determining the release of all the materials in the plant.
Eliyahu M. Goldratt